How Long Does It Take to Build a Mobile App? Scope and Platform

12 November 2026

How long does it take to build a mobile app? Published ranges put a small app at roughly two to four months and a large one at six months to a year or more. Those numbers cover the build. A mobile app also has a calendar item a web app lacks: store review, plus, for new Google Play personal accounts, a mandatory closed test. This guide gives the ranges with their sources, shows what a second platform adds, and lists the gates after the last feature. Figures were checked on October 15, 2026.

Published ranges: how long does it take to build a mobile app

Five public guides, five sets of bands. They agree on the order of magnitude and on little else.

Source Small Medium Large
Simpalm 11 to 13 weeks 24 to 30 weeks 37 to 50 weeks
Startup Grind 10 to 12 weeks 23 to 25 weeks 35 to 38 weeks
Anything (AI builder vendor) 2 to 4 months 4 to 7 months 5 to 9 months for an MVP, 9 to 18+ for a full program
Itransition several weeks to 3 months 3 to 7 months 7 to 12+ months
Aetherius a few weeks to 2 or 3 months 3 to 6 months 6 months to over a year

Two of these publish full stage tables, Simpalm and Startup Grind, and their totals land close together. Startup Grind’s article carries no date and builds its bands on an Instagram-style example, so treat it as the older of the two. The rest give bands without a breakdown.

Simpalm’s table splits its totals into stages, which shows where the weeks sit:

Stage (Simpalm) Small Medium Large
Requirements and scoping 2 to 3 weeks 4 to 6 weeks 6 to 8 weeks
UI and UX design 3 to 4 weeks 6 to 8 weeks 8 to 12 weeks
Development and testing 5 to 6 weeks 12 to 14 weeks 20 to 26 weeks
Beta testing and launch 1 week 2 weeks 3 to 4 weeks

Development and testing take the largest single share at every size, but for a small app scoping and design together come close to it. The useful reading is not a number. It is that the size of the app, defined by screens, features and integrations, dominates everything else. Simpalm defines size by screens and functions: a small app in its table has around 5 to 12 screens and 1 to 3 main functions, a large one runs to 15 to 25 screens and about 18 to 25 functions. So how long does it take to build a mobile app? The answer begins with a feature list, not a calendar.

What a second platform adds

Most mobile projects target iOS and Android, and how you do that is the biggest single lever on the calendar. How long does it take to build a mobile app on one codebase compared with two? Every source that quantifies it is a vendor.

  • Anything says a second platform with native parity adds roughly 1.3 to 1.6 times the engineering effort.
  • Base44 says building separate native apps roughly doubles development time compared with one cross-platform build.
  • Aetherius says Kotlin Multiplatform can double the speed of development by sharing business logic.
  • Itransition says cross-platform development lets teams launch for different audiences sooner.

These do not agree, and none is an independent benchmark. What they share is the direction: one shared codebase tends to shorten the build, and separate native apps lengthen it. What it costs you in fit, performance or platform features is a different question, which we cover in our article on cross platform app development. For the calendar, ask your vendor for the schedule under both approaches, and what is shared in each.

Store gates between the build and launch

How long does it take to build a mobile app once the last feature ships? Part of the answer comes after the build. Three items sit at the end of the calendar and are not under a vendor’s control.

How long does it take to build a mobile app: the store gates before launch, from the Google closed test to Apple and Google review and release
Release gates between the build and launch, from Apple and Google help pages checked October 15, 2026. They are not under a vendor's control.

Apple review. Apple’s App Review page says review works around the clock and typically covers at least 50% of submissions in less than 24 hours and 90% in less than 48 hours. Incomplete submissions can be delayed or fail. Apple also says that over 40% of unresolved issues relate to guideline 2.1, App Completeness: crashes, placeholder content and incomplete information. Provide a demo account if features need sign-in, or review may be delayed.

Google Play review. Google’s help page says certain apps may be subject to extended reviews, with review times of up to 7 days or longer in exceptional cases.

The Google Play closed test. Personal developer accounts created after November 13, 2023 must run a closed test with at least 12 testers opted in continuously for 14 days before applying for production access. Google’s page covers personal accounts; check what applies to an organization account before you rely on either reading. That fortnight can start only once the app is set up in Play Console, so it belongs on the schedule, not at the end of it. We covered the same rule in our eight-week MVP plan.

One more dated requirement: since August 31, 2026, new apps and updates for most device types must target Android 16 (API level 36) or higher on Google Play, with an extension to November 1, 2026 on request. Confirm the current rule before you plan, since it changes by year.

None of this is a delay if you plan for it. All of it is a delay if you discover it in the last week.

What else moves the date

Beyond size and platform, the sources repeat the same short list.

  • Integrations. Anything gives a rule of thumb of 1 to 2 weeks per third-party integration for clean connectors, with extra buffer in regulated settings. That is one vendor’s figure, so use it to compare quotes, not to plan.
  • Late changes. Anything describes swapping a simple polling approach for true real-time as a change that added several weeks, because it touched authentication, data models and testing. Itransition makes the general point that mid-project changes lead to scope creep and a longer project.
  • Unclear first version. Aetherius says a missing list of must-have features for the MVP is one of the biggest reasons a timeline slips.
  • Testing. Aetherius puts app testing at usually 1 to 3 weeks depending on size and complexity.
  • Decision speed. Anything calls approvals and feedback delays a high hidden cost.

If you want the web equivalent, our guide to how long a web app takes covers the same factors without the store gates. The stages of app development explain what you receive at each step.

A schedule that protects the launch date

How long does it take to build a mobile app? Nobody can answer that from the outside, but you can order the work so that waits overlap with building:

  1. Week one: accounts and devices. Open developer accounts and test devices before they block anything. Know which account type you hold.
  2. Define the first version in writing. One user role, one core flow. Our MVP guide shows how to cut.
  3. Start the closed test as soon as the app is set up. Recruit testers while the build is still in progress.
  4. Submit early to find out what review says. A first rejection is cheaper at a test build than in launch week.
  5. Keep a buffer after the last feature. Review, rejection and resubmission are scheduled time, not exceptions.

Questions that make a mobile timeline usable

How long does it take to build a mobile app, in your vendor’s plan? Ask these in writing, because a range without its assumptions is only a guess:

  • Which platforms does the range cover, and with which approach: native or cross-platform?
  • How many screens, user roles and integrations does it assume?
  • Is the backend included?
  • Which store gates does the plan include, for which account type?
  • What does a change request do to the date?

A vendor who answers these has a range with reasons. A vendor who cannot is quoting from a brochure.

Send the brief, get a written scope

techcraftz puts scope, milestones and the estimate in writing before the first line of code, then hands over the code, the store accounts and the keys. How long does it take to build a mobile app like yours? We do not publish a standard timeline, because the answer depends on the app. If you want a real answer for your product, see our mobile app development page and how we work. If you need to test the idea first, read about MVP development. Get a written scope.

Last checked: October 15, 2026. Store rules and published ranges change; verify them before you plan a launch.

Talk to us about your project

Tell us what you need. We help you scope the build, the milestones and a realistic estimate.

View services
Blog

Related guides

Start now

Brief in. Scope out.

Tell us what you need. We will map out the approach, the stages and a written estimate.

08 / Contact

Tell us about your project

Fill in the short form below. We will reply with questions or next steps and, once the scope is clear, a written estimate.

Service area
Worldwide (remote)

Enter your name.

Enter a valid email so we can reply.

Choose a project type.

Tell us briefly what you want to build.

Your details are used only to respond to this request.